Ac load bank control mode

The load bank should test the equipment for relevant items, including but not limited to the following points.


500kw load bank
 
Load test control modes include:
1. Load test: can load any power within the rated value, measure and display the generator set steady-state voltage, current, active power, reactive power, apparent power, power factor, frequency, operating time and other parameters.
2. One-click loading and unloading: Whether manual switch or software control is adopted, the power value can be set first, and then the total loading switch is started, so that the load will be loaded according to the preset value, so as to avoid the load fluctuation in the process of power adjustment.
3. Control mode selection: You can manually or intelligently control the load.
4. Manual control: load is equipped with local control panel, and divided into a number of power gears, can be controlled by the switch loading. Manual control directly controls the main loop, even if the control module or communication interface failure, manual control can directly operate the load hardware.
5. Intelligent control: through the data management software on the computer to control the load, automatic loading, and display, record and manage the test data, generate all kinds of curves, charts, and support printing. It can be controlled remotely through RS485 interface. Also through the RS232 interface, in the machine side for intelligent control of load.
6. Interlock of control mode: the system is equipped with control mode selection switch. After selecting any control mode, operations carried out by other modes will be invalid to avoid conflicts caused by multiple operations.
7. Local instrument display data: through the local measuring instrument can display voltage, current, active power, reactive power, apparent power, power factor, frequency and other parameters.